Division B
Acceptable Solutions

Part 5 — Environmental Separation

Section 5.5. Vapour Diffusion

(See Appendix A and Part 10.)

5.5.1. Vapour Barriers

5.5.1.1. Required Resistance to Vapour Diffusion
(See Appendix A.)
1) Intent StatementWhere a building component or assembly is subjected to differentials in temperature and water vapour pressure, the properties and position of the materials and components in those components or assemblies shall be such that they control vapour diffusion or permit venting to the exterior so as to minimize the accumulation of condensation in the building component or assembly.
2) Intent StatementExcept as provided in Sentence (3), a vapour barrier shall be installed to provide the principal resistance to water vapour diffusion.
3) Intent StatementA vapour barrier is not required where it can be shown that uncontrolled vapour diffusion will not adversely affect any of
a) the health or safety of building users,
b) the intended use of the building, or
c) the operation of building services.
5.5.1.2. Vapour Barrier Properties and Installation
(See A-5.3.1.2. in Appendix A.)
1) Intent StatementThe vapour barrier shall have sufficiently low permeance and shall be positioned in the building component or assembly so as to
a) minimize moisture transfer by diffusion, to surfaces within the assembly that would be cold enough to cause condensation at the design temperature and humidity conditions, or
b) reduce moisture transfer by diffusion, to surfaces within the assembly that would be cold enough to cause condensation at the design temperature and humidity conditions, to a rate that will not allow sufficient accumulation of moisture to cause deterioration or otherwise adversely affect any of
i) the health or safety of building users,
ii) the intended use of the building, or
iii) the operation of building services.
(See Appendix A.)
2) Intent StatementCoatings applied to gypsum wallboard to provide required resistance to vapour diffusion shall conform to the requirements of Sentence (1) when tested in accordance with CAN/CGSB-1.501-M, “Method for Permeance of Coated Wallboard.”
3) Intent StatementCoatings applied to materials other than gypsum wallboard to provide required resistance to vapour diffusion shall conform to the requirements of Sentence (1) when tested in accordance with ASTM E 96/E 96M, “Water Vapor Transmission of Materials,” by the desiccant method (dry cup).